Army Corps completes reservoir for Everglades restoration

Author: Associated Press
Published:
FILE – Storm clouds form over the Florida Everglades which are facing an environmental storm caused by pollution and man’s interference with the ecosystem. The U.S. Army Corps of Engineers has completed work on a $339 million Everglades restoration project aimed at cleansing water runoff before it flows into a troubled Florida river. Corps and local officials held a ceremony Friday, Nov. 20, 2021, for the 12,000-acre (4,800-hectare) project in Martin County known officially as the C-44 Reservoir and Stormwater Treatment Area. It’s a key part of a broader effort to rescue the vast Florida Everglades. (AP Photo/Phil Sandlin, File)

The U.S. Army Corps of Engineers has completed work on a $339 million Everglades restoration project aimed at cleansing water runoff before it flows into a troubled Florida river.

Corps and local officials held a ceremony Friday for the 12,000-acre (4,800-hectare) project in Martin County known officially as the C-44 Reservoir and Stormwater Treatment Area. It’s a key part of a broader effort to restore the vast Florida Everglades.

The reservoir will capture, store and clean fertilizer-laden runoff from farms and development before it is routed into the St. Lucie River and ultimately the Indian River Lagoon. Both have been plagued by harmful algae blooms and other long-term problems associated with water pollution that threatens wildlife and human health.

“I think it’s huge” for the east coast,” said Chauncey Goss, chair of the South Florida Water Management District. “Not only symbolically, but it’s also going to be taking water, cleaning it up and helping to get rid of some of these discharges, which is really the goal of all of this.”

The project can store 19.7 billion gallons (71 billion liters) of water, according to state water managers. It will use plants such as cattails to suck up about 35 metric tons of phosphorus every year before the water makes its way into the St. Lucie River.

The C-44 canal, first dug in 1923, was built to divert potential flood water from Lake Okeechobee to the river flowing east. Some environmental groups say the new reservoir will still permit too much fresh water to flow into the river and coastal estuaries, upsetting the natural balance.

“The bottom line: Too much freshwater is too much freshwater. It’s going to be cleaner water with less sediment. That’s all good. But a gallon’s a gallon, and it’s going to come through those gates eventually,” said Indian Riverkeeper Mike Conner.

The project is part of the Indian River Lagoon-South Project, which is a component of the Comprehensive Everglades Restoration Plan. That long-term program encompasses 68 projects designed to restore, protect and preserve the Everglades ecosystem.

The new C-44 reservoir is the first fully completed part of the overall restoration plan.

Copyright ©2024 Fort Myers Broadcasting. All rights reserved.

This material may not be published, broadcast, rewritten, or redistributed without prior written consent.