Fort Myers Beach Street project list: Names, work and times

Published: Updated:
The effects of Hurricane Hermine caused street flooding in Fort Myers Beach.

Fort Myers Beach has provided the schedule of street improvements to decrease flooding in areas. Below is a list of streets they are targeting first.

Williams Drive

  • Water and storm
  • March 11
  • Estimated finish time: June 10

Bahia Via

  • Water and storm
  • March 11
  • Estimated finish time: May 6

Seminole Way (Priority Street)

  • Storm drain
  • April 15
  • Estimated finish time: April 26

Pepita Street (Priority Street)

  • Storm drain
  • April 17
  • Estimated finish time: May 2

Estrellita Drive

  • Storm drain
  • April 22
  • Estimated finish time: June 3

Coconut Drive

  • Storm drain
  • April 29
  • Estimated finish time: May 17

Sabal Drive

  • Storm drain
  • May 3
  • Estimated finish time: May 20

Hibiscus Drive

  • Storm drain
  • May 7
  • Estimated finish time: May 24

Randy Lane

  • Storm drain
  • May 20
  • Estimated finish time: June 10

Avenida Carita

  • Storm drain
  • May 27
  • Estimated finish time: June 17

Indian Bayou Drive

  • Outfall Improvement
  • June 4
  • Estimated finish time: June 20

Widgeon Terrace

  • Storm drain
  • June 11
  • Estimated finish time: July 3

Flamingo Street

  • Storm drain
  • June 18
  • Estimated finish time: July 12

Curlew Street

  • Storm drain
  • June 21
  • Estimated finish time: July 11

Egret Street

  • Storm drain
  • July 4
  • Estimated finish time: July 22

Ibis Street

  • Storm drain
  • July 12
  • Estimated finish time: July 29

Bayview Boulevard

  • Storm drain
  • July 15
  • Estimated finish time: Aug. 30

Anchorage Street

  • Storm drain
  • July 23
  • Estimated finish time: Aug. 23

St. Peters Drive

  • Storm drain
  • July 30
  • August 31